Nad Al Sheba Gardens 3 handover date: what happens next
Nad Al Sheba Gardens 3 is nearly built, but its planned date has passed and Meraas has given no new one. The last inspection is a few months old, so the work has probably moved on since. When Meraas’ notice comes, we can do the whole handover for you.
Developer’s render · MeraasHandover date
Not setYour handover notice gives the date that counts.
Next step
The completion certificateThen Meraas’ handover notice
Homes
2353- to 5-bed villas and townhouses
Developer
MeraasNad Al Sheba Gardens
Where Nad Al Sheba Gardens 3 is now, and the steps to your keys
Nad Al Sheba Gardens 3 construction update: each step to your keys
Nad Al Sheba Gardens 3 is further along than any other phase Meraas is building in the community, and the completion certificate comes next. We send you every new inspection the day it is recorded.
Work started
The date registered with the Land Department.
Planned date
The completion date registered with the Land Department, now passed.
Last inspection
97% built.
Nearly built, and past its planned date. Meraas has not published a new date.
New inspection results
We send you each one the day it appears.
100% and the completion certificate
After that, Meraas starts sending handover notices.
Handover notice
Meraas asks for the last payment and the fees, and tells you when the villa inspection and the key collection can be booked. We book both for you.
Snagging
We check the villa, the roof and the garden levels before you accept the keys, and send Meraas the list of faults.
Keys
We open the utility accounts in your name, then collect the keys. If the developer requires a power of attorney, we arrange it with you remotely.
Furnishing
If you want it furnished, we design and furnish the villa so it is ready for a tenant.
Your garden
We design it, get Meraas’ approval and build it, so the villa is finished when a tenant moves in. Your garden →
Your first tenant
We advertise the villa once it is ready, find a tenant on a yearly contract and send the rent to you abroad.
Source: Dubai Land Department.
Handover costs
Nad Al Sheba Gardens 3 handover costs to budget for
At the Nad Al Sheba Gardens 3 handover you pay what is left under your sales contract. Then come Meraas’ fees, service charge in advance, a refundable DEWA deposit and the title deed fee.
Typical figures for 2026. Meraas’ bill has the exact amounts, and we check them with you line by line.
Furnish or not?
Nad Al Sheba Gardens 3: furnished, or let empty?
Meraas hands over Nad Al Sheba Gardens 3 homes empty, to let as they are or furnish first. Most are three-beds, so many similar homes will be offered to tenants at once, beside the finished houses in Nad Al Sheba Gardens 2.
Nad Al Sheba Gardens 3’s homes by layout
Which is yours?
Most homes here are 3-beds: 174 of them.
Source: Dubai Land Department
A similar villa in another project, empty and furnished


- ✓Stands out next to similar homes on rental websites
- ✓Tenants see how they would live in it
- ✓Ready to move into, for tenants who don’t want to buy furniture
What this means
A furnished villa stands out among many similar ones. Interior design and furniture let tenants see in the photos how they would live there, and the villa can be let to tenants who don’t want to buy furniture.
We plan the interior of your Nad Al Sheba Gardens 3 home around its rooms, furnish it after the keys and photograph it for the advert.
Garden
Nad Al Sheba Gardens 3: from sand to finished garden
We expect Nad Al Sheba Gardens 3 gardens to come as bare sand, like most new Dubai villas. We plan the landscaping with you, get Meraas’ approval and build it after the keys.
Designed around how you will use it
The same garden, at the keys and finished


Whatever you plan for the house
The garden is ready when your family arrives, and nobody is digging behind the house in your first months.
When many similar houses are offered at once, a finished garden gives yours a reason to be chosen first.
A buyer sees a finished home, not a garden they still need to plan and pay for.
What this means
Meraas must approve the garden plan before work begins, and work done without that approval may have to be removed. So the approval comes first, and the garden is built just once.
Send us your Nad Al Sheba Gardens 3 plot number, and we reply with a first garden plan and how we would build it.
Buildings around
Nad Al Sheba Gardens 3 and the other phases around it
In Nad Al Sheba Gardens and around it, two villa projects are finished. Of those still being built, none is as far along as phase 3.
Already finished
Being built
Source: Dubai Land Department
What this means
Phase 4 is the closest behind, and still well short of finished. So the homes tenants will compare yours with are the finished ones in Nad Al Sheba Gardens 2 and MAG 22. For a while, phase 3 should be the newest choice in the community.
The developer
Meraas handovers: how they work at Nad Al Sheba Gardens 3
How Meraas hands over homes, and how many of its projects are past their date.
About Meraas
Meraas sends its handover notices once the completion certificate is issued, and the notice says how to book the villa inspection and the keys. Nad Al Sheba Gardens 2 came about a year after its planned date, but was let within weeks.
Handover
How handover is booked
Meraas’ 10 projects in the Land Department records
- Finished4
- Being built, date still ahead2
- Being built, past their date yours1
- Being built, no finish date given3
Source: Dubai Land Department
What this means
Most of Meraas’ finished projects came in on time, and phase 3 is its only project being built that is now past its date. Phase 2 shows a late date need not slow the letting. We follow Meraas for you and act the day your notice comes.
We deal with Meraas for your Nad Al Sheba Gardens 3 home from the notice to the keys, while you stay abroad.
Location
Nad Al Sheba Gardens 3 location, and what is around it
Nad Al Sheba Gardens is Meraas’ community of villas and townhouses beside Meydan and its racecourse. It has open gardens and parks, and Downtown Dubai and Dubai International airport are a short drive away.
By car
Around you
Questions
Nad Al Sheba Gardens 3: what owners ask
Something not here? Ask us on WhatsApp; we reply within 30 minutes.
When is the Nad Al Sheba Gardens 3 handover date?
There is no handover date yet. The planned date, meaning the completion date registered with the Land Department, was 19 April 2026 and has passed, and Meraas has not given a new one. Handover starts once the homes are finished and certified, and the date in your handover notice is the one that counts.
Is Nad Al Sheba Gardens 3 late?
Yes, against its planned date. In the 43 months from the start of work to the last inspection, the homes went up at about 2.3% a month, and there is no date still ahead to measure that speed against. The last stretch of a build usually runs slower, so only the next inspection will show how close it is.
How does snagging work at Nad Al Sheba Gardens 3?
Before you take the keys, the villa is checked for faults: the roof and terraces for standing water, the AC in every room, the seals of doors and windows, and the slope of the plot. We do this villa inspection, send Meraas the list of faults and come back to check the repairs.
Will my Nad Al Sheba Gardens 3 garden be finished at handover?
We do not expect so. The plot will most likely come as bare sand. We can plan a garden for it, have Meraas approve the plan and then build it.
What do I pay at the Nad Al Sheba Gardens 3 handover?
Whatever your sales contract leaves to be paid on completion, plus Meraas’ fees, the service charge paid in advance, a DEWA deposit of AED 4,000 that you get back later, and the title deed fee. Meraas’ bill shows the exact amounts, and we check them with you before you pay.
Can I do the Nad Al Sheba Gardens 3 handover from abroad?
Yes. We act for you: we check Meraas’ bill, carry out the villa inspection, put DEWA in your name and collect the keys. If the developer requires a power of attorney, we arrange it with you remotely.
Our service
Everything from Meraas’ first email to a finished home
For your Nad Al Sheba Gardens 3 home we check Meraas’ bill, inspect the villa from the roof and terraces to the slope of the plot, and build the garden on the bare sand. Then come interior design, furnishing, a tenant and property management.
What we do for your villa
- 01
The handover with Meraas.
- 02
The inspection for faults.
- 03
Design and furnishing.
- 04
A tenant, and the rent sent to you.
- 05
Looking after it year to year.
Free updates and a handover plan
Your handover plan for Nad Al Sheba Gardens 3
Tell us which home is yours. We tell you the day Meraas’ notice goes out, and give you an early estimate of your handover bill, free.
On a computer? Scan to open WhatsApp on your phone, with the message ready.