In Motor City · by Sobha

Being built

Sobha Solis handover date and how the build is going

Sobha Solis has a planned date at the end of 2028, still more than two years off. The latest inspection on record is six months old, so the towers have likely risen since. We pass on every new result and what it means for you.

BuiltChecked by the Land Department · 5 May 2026
13%builtNext inspection awaited
5 May 2026Last inspection31 Dec 2028Planned finish date
Sobha Solis in Motor City, the developer’s render: four slim dark-glass towers in a stepped row, the tallest with a gold Sobha crown, gold rooftops and a landscaped podium between them, with low townhouses to the rightDeveloper’s render · Sobha

Handover date

Dec 2028

The registered completion date. Your handover notice gives the date that counts.

Next step

A new inspection

Then the completion certificate and Sobha’s notice

Homes

2,310

Mostly 1-bedroom flats in four towers of 27 to 47 floors, sold furnished

Developer

Sobha

Motor City

Where Solis is now, and the steps to your keys

Where Sobha Solis stands, and what comes before your keys

Solis is early in its build and sits in the middle of the Motor City projects under way, with several ahead of it. Its last inspection is older than any of theirs. We send you each inspection as it appears.

Jan 2025
✓

Sales opened

Sobha launched Sobha Solis, its first project of 2025, and put the flats on sale.

3 Oct 2024
✓

Work started

The start date on the Land Department register.

5 May 2026
✓

Last inspection

13% built.

Today

In the early stages of building. The planned date of 31 December 2028 is still ahead.

To your keys
Next

New inspection results

We send you each one the day it appears. Progress over time →

100% and the completion certificate

After that, Sobha starts sending handover notices.

Handover notice

Sobha asks for the last payment and the fees, and tells you when the flat inspection and the key collection can be booked. We book both for you.

Snagging

We check the flat before you accept the keys, and send Sobha the list of faults.

Keys

We open the utility accounts in your name, then collect the keys. If the developer requires a power of attorney, we arrange it with you remotely.

After the keys

Your first tenant

We advertise the flat, find a tenant on a yearly contract and send the rent to you abroad.

Sources: Dubai Land Department; sales start: Sobha’s launch release.

Progress over time

Sobha Solis completion date: is it moving fast enough?

The planned date for Solis is the last day of 2028. The two cards set the pace it has kept since work started against the pace it now needs to get there.

0%50%100%20242025202620272028202920302031203220332034203520362037Today13% at the last inspection, 5 May 2026Dec 2028 · registeredLate 2036 · speed so far0%50%100%2024202620282030203220342036Today13% · 5 May 2026Dec 2028Late 2036

Source: Dubai Land Department

Speed so far

0.7% a month

13% in the 19 months from October 2024 to the last inspection

Needed for 31 December 2028

~2.7% a month

the remaining 87% in the 32 months from the last inspection to the planned date

What this means

For now Solis is moving slower than its date asks. Early building is often slow, so the speed can still pick up, but it would have to rise a lot. Keep any plans for a tenant or a move flexible until the inspections show that rise.

Buildings around

Sobha Solis and the other projects going up in Motor City

The list shows the projects being built around Solis in Motor City and how far each had got at its latest inspection. Several are further along, and some are behind.

The CommunityAQUA PropertiesWas due Oct 2025
95%
Capital OneThe CircuitDue Feb 2027
20%
MonarchZane DevelopmentsWas due Oct 2026
20%
Sobha OrbisSobhaDue Dec 2028
18%
TakayaTakayaDue Dec 2027
16%
SolisYoursSobhaDue Dec 2028
13%
Velos ResidenceCity ViewDue Oct 2028
7%
MirdadMirdadDue Dec 2028
6%
15 CascadeImanDue Sep 2028
6%
Sierra by ImanImanDue Jun 2029
4%
Ananda ResidencesTiger GroupDue May 2028
3%

Source: Dubai Land Department

What this means

Sobha Orbis next door has the same planned date as Solis and is also mostly one-beds. If both keep to that date, owners of thousands of similar flats will look for tenants in Motor City in the same season. A flat ready for a tenant soon after the keys has the edge.

Service charge

Sobha Solis service charge: what to set aside

No service charge is approved for Sobha Solis yet, so this is an estimate from what owners pay, through Mollak, in six finished residential buildings in Motor City. A sunken pool and branded gym may push the Solis rate higher.

Your yearly service charge

~AED 9,390

about AED 780 a month

Lowest nearbyAED 7,680Highest nearbyAED 10,140

Your size × the middle rate of the residential buildings nearby. A Solis one-bed is about 545 sq ft.

The same flat in each residential building nearby, a year

AED a yearper sq ft
Norton Court 3AED 7,68014.10
Weston Court 2AED 8,06014.78
Widcombe House 2AED 9,34017.13
Solisyours, estimated~AED 9,39017.23
Easton CourtAED 9,44017.33
Terrace Apartment 2AED 9,77017.93
Fox Hill 7AED 10,14018.61

Source: Dubai Land Department service charge index, via DXBinteract

Handover costs

Sobha Solis handover costs: the biggest line

If you are on the payment plan that most listings show, the final instalment due at handover is by far the largest part of the bill. The fees around it are small next to it.

Last payment40% of the priceIf you are on Sobha’s 60/40 plan. On that plan 40% is due at handover, with nothing due after the keys. Most listings for Sobha Solis quote 20% at booking, 40% while it is built and 40% at handover; one quotes 10% at booking and 50% while it is built. Your sales agreement shows yours.
Sobha’s handover and admin feesSobha doesn’t publish these
Service charge, paid in advanceShown on your bill
Electricity and water (DEWA)AED 2,000 deposit + about AED 130 fees
Air conditioning (cooling)The deposit depends on the company
Title deedAbout AED 250–600
Snagging (checking the flat for faults)From AED 1,599

Typical figures for 2026. Sobha’s bill has the exact amounts, and we check them with you line by line.

While you wait

Sobha Solis: what to do until the keys

Four things to do now, so your Solis handover goes smoothly from abroad.

01

Keep to your instalments

If you are on the 60/40 plan, the payments during the build come first and 40% waits for handover. Keep every receipt, because Sobha’s final bill is checked against them.

02

Pick who takes the handover

Each flat comes with furniture and kitchen appliances, so there is more to check than walls and taps: every item against the list in your agreement. We can do the flat inspection and the steps after it for you. Handover management →

03

Live in it or let it

Solis flats arrive furnished, so the choice is mainly whether you move in or find a tenant. If you let, plan how your flat will stand out among many similar one-beds. Our services →

04

Follow the inspections

The planned date is the end of 2028, and only the inspections show whether Solis is on course. We write after each one, and again when Sobha begins sending handover notices.

Appoint Key Homes for your Sobha Solis handover now, and the bill check, flat inspection and key collection are planned before Sobha’s notice arrives.

Get my handover plan

The developer

How Sobha hands over its towers, and how it keeps to dates

How Sobha hands over homes, and how many of its projects are past their date.

About Sobha

Sobha sends each owner a notice with the bill and the steps for the handover. On the Land Department record, Sobha has very few projects past their planned date. Solis is one of its two large projects in Motor City.

Handover

How handover is booked

BookingSobha customer care, after the handover notice
Flat inspection and keysSet out in the handover notice
Phone800 SOBHA (76242)
EmailCustomerCare@sobharealty.com

Sobha’s 47 projects in the Land Department records

  • Finished23
  • Being built, date still ahead yours13
  • Being built, past their date1
  • Being built, no finish date given10
Homes in finished projects8,843
Projects being built now24

Source: Dubai Land Department

What this means

Sobha’s record is a good sign, but it does not tell you when Solis will be done; several neighbours are further along and Solis started slowly. The inspections will tell. If you live abroad, we handle the handover for you when the notice comes.

Write to us and we keep watch on Solis for you, from each inspection to the day Sobha’s notice arrives.

Get my handover plan

Location

Where Sobha Solis is: Motor City, by the Dubai Autodrome

Solis stands in Motor City, close to the Dubai Autodrome and next to Sobha Orbis. Sheikh Mohammed Bin Zayed Road and Al Qudra Road are the roads out, towards Dubai Hills Mall, Mall of the Emirates and the coast.

By car

Dubai Hills Mall~15 min
Mall of the Emirates~20 min
Burj Al Arab~25 min

Around you

Next doorDubai Autodrome
NeighbourSobha Orbis, Sobha’s other project in Motor City
RoadsSheikh Mohammed Bin Zayed Road and Al Qudra Road
In the projectA sunken pool and an Arsenal-branded gym, according to Sobha’s launch release

Questions

Solis: what owners ask

Something not here? Ask us on WhatsApp; we reply within 30 minutes.

When is the Sobha Solis handover date?

Sobha Solis is planned for 31 December 2028, the completion date registered for it with the Dubai Land Department. Solis was 13% built at the inspection of 5 May 2026. The keys come after completion, so your own date will be the one in Sobha’s handover notice.

Is Sobha Solis on track for 2028?

Not so far. Since work started it has risen by about 0.7% a month, and it needs about 2.7% a month from the last inspection to finish by the planned date. Early building is often slow, so the pace may still rise. We will see from the next inspections if it does.

What should I check in my Sobha Solis flat before taking the keys?

The cooling in every room, windows and balcony doors, taps and drains, and the finish of walls and floors. As the flats come furnished, every piece of furniture and each kitchen appliance is checked against your agreement. Faults reported in writing before you accept are Sobha’s to fix.

How much do I pay at the Sobha Solis handover?

If you are on the 60/40 plan, 40% is due at handover, with nothing after the keys. Sobha’s fees, the first service charge, the DEWA deposit and the title deed fee come at the same time. Your sales agreement shows your own plan.

What will the Sobha Solis service charge be?

The Sobha Solis service charge has not been set yet. Owners in finished residential buildings in Motor City pay roughly AED 14 to 19 per sq ft a year, about AED 17 in the middle. With its pool and gym, the Solis rate may be higher.

Can I receive my Sobha Solis flat while living abroad?

Yes, you do not need to fly in. When Sobha’s notice arrives, we go through its bill, carry out the flat inspection, set up DEWA in your name and pick up the keys for you. If the developer requires a power of attorney, we arrange it with you remotely.

Our service

From Sobha’s notice to a tenant in your Solis flat

Until handover we follow every inspection at Solis. Then we check Sobha’s bill, test the flat and the furniture it comes with, and collect the keys. After that, interior design helps your flat stand out from its many neighbours, and our property management team looks after the tenant.

Illustrative photo

What we do for your flat

  1. 01

    The handover with Sobha.

  2. 02

    The inspection for faults.

  3. 03

    Design and furnishing.

  4. 04

    A tenant, and the rent sent to you.

  5. 05

    Looking after it year to year.

Free updates and a handover plan

Your handover plan for Solis

Leave your details and we send you each new inspection of Sobha Solis, with what it means for your handover date.