In Dubailand Residence Complex · by Time Properties
Time 2 by Time Properties handover date: 87% built
Time 2 is almost finished, but its planned date and the Q2 2026 date listings gave have both passed. The last inspection is months old, so the tower is probably further along than the record shows. We watch for the next one and prepare your handover now.
Developer’s render · Time PropertiesHandover date
Not setThe date listings gave, Q2 2026, has passed. Your handover notice gives the date that counts.
Next step
The completion certificateThen Time Properties’ handover notice
Homes
304Studios to 3 bedrooms, in one 21-floor tower
Developer
Time PropertiesDubailand Residence Complex
Where Time 2 is now, and the steps to your keys
Time 2 construction update, and every step to your keys
Time 2 is in its last stage of building, and four towers around it in Dubailand Residence Complex (DLRC) are further along. Next come the completion certificate and Time Properties’ handover notice. We send you each new inspection.
Sales opened
Sales started, according to a listing. The Land Department record gives no start date for the building work.
Last inspection
87% built.
Still being built. Both the planned date and the date listings give have passed, and no new date has been published.
New inspection results
We send you each one the day it appears.
100% and the completion certificate
After that, Time Properties starts sending handover notices.
Handover notice
Time Properties asks for the last payment and the fees, and tells you when the flat inspection and the key collection can be booked. We book both for you.
Snagging
We check the flat before you accept the keys, and send Time Properties the list of faults.
Keys
We open the utility accounts in your name, then collect the keys. If the developer requires a power of attorney, we arrange it with you remotely.
Furnishing
If you want it furnished, we design and furnish the flat so it is ready for a tenant.
Your first tenant
We advertise the flat, find a tenant on a yearly contract and send the rent to you abroad.
Source: Dubai Land Department.
Handover costs
Time 2 handover costs to budget for
At Time 2 the last payment depends on your plan. If you are on the plan Property Finder quotes, most is paid while the tower is built and little is left at the keys.
Typical figures for 2026. Time Properties’ bill has the exact amounts, and we check them with you line by line.
Snagging
Snagging at Time 2: what to check first
From Time Properties’ notice until you sign for the keys, every fault you report in writing is Time Properties’ to repair. At Time 2 we start with the four checks below.
Ask for your date at once
The last inspection on record is from April 2026, so the notice may come with little warning. We ask for your flat inspection date the day it arrives, before the slots fill.
Kitchen, bathroom and cooling
Most homes here are studios and one-beds. In a small flat a tenant feels a weak air conditioner or a slow drain at once, so we test each one.
Windows on the upper floors
The tower has 21 floors on the Land Department record. Higher up, wind and dust find every weak seal, so we check that each window and balcony door closes tight.
Dust from the sites around
Many other towers in DLRC are still being built. Their dust gets into air conditioning filters, window tracks and drains, so we open and check each of them.
What this means
Send Time Properties every fault in writing, with photographs, before you sign for the keys. What you list then is repaired at Time Properties’ cost, and we check each repair for you.
From AED 1,599 we do the flat inspection at Time 2 for you and send Time Properties the snagging report, with a photograph of each fault.
Furnish or not?
Furnish your Time 2 flat, or let it empty?
Two in three homes at Time 2 are one-beds, and Bliss Tower and Cove Edition by Imtiaz, among others nearby, are close to their keys as well. Their owners and Time 2’s may look for tenants in the same months.
Time 2’s homes by layout
Which is yours?
Most homes here are 1-beds: 199 of them.
Source: Dubai Land Department
A similar flat in another building, empty and furnished


- ✓Stands out next to similar flats on rental websites
- ✓Tenants see how they would live in it
- ✓Ready to move into, for tenants who don’t want to buy furniture
What this means
When tenants can choose between many new one-beds and studios, a furnished flat often lets sooner. Interior design that suits a small layout and good furniture help yours stand out.
Send us your layout and we reply with a furnishing plan, its cost and the rent it may bring, ready before the keys.
Buildings around
Time 2 and the towers around it in DLRC
Time 2 is one of eight towers being built in Dubailand Residence Complex (DLRC), near finished buildings such as Time 1, its sister tower.
Already finished
Being built
Source: Dubai Land Department
What this means
Dalmore Tower, AG 7even and two more towers nearby are close to their keys as well, so the owners of about 1,000 new flats may look for tenants within months of each other. Plan the letting before the keys, so your flat is not one of many waiting for a tenant.
The developer
Time Properties handovers: how they work and its record on dates
How Time Properties hands over homes, and how many of its projects are past their date.
About Time Properties
Six Time Properties projects on the Land Department record are finished, Time 1 among them. Of the two being built, Time 2 is past its planned date. Your handover notice will set out the bill and how the keys are booked.
Handover
How handover is booked
Time Properties’ 8 projects in the Land Department records
- Finished6
- Being built, date still ahead1
- Being built, past their date yours1
- Being built, no finish date given0
Source: Dubai Land Department
What this means
All six earlier Time Properties projects on the record are finished, but Time 2 is late against both dates and the last inspection is from April 2026, so your notice could arrive with little warning. While you are abroad, we reply to it and handle each step for you.
Write to us now and we tell you when Time Properties starts sending notices for Time 2, and what yours will ask you to pay.
Location
Time 2 location, and what is around it
Time 2 stands in Dubailand Residence Complex, an area of new residential towers between Al Ain Road and Emirates Road. Time 1, its finished sister tower, is in the same area. No Metro station is close by.
By car
Around you
Questions
Time 2: what owners ask
Something not here? Ask us on WhatsApp; we reply within 30 minutes.
When is the Time 2 handover date?
The planned date, the completion date registered with the Dubai Land Department, was 1 June 2026 and has passed. Listings gave Q2 2026, which has also passed, and Time Properties has not published a new date. The tower was 87% built at the inspection of 28 April 2026. Your own date comes in Time Properties’ handover notice.
Is Time 2 by Time Properties delayed?
Yes. It has passed both the planned date of 1 June 2026 and the Q2 2026 date listings gave. Counted from the start of sales, it has gone up about 2.1% a month, but no date is left ahead to measure that against. Only a new Land Department inspection will show how far it is now.
What should I check in my Time 2 flat before accepting it?
The air conditioning, the kitchen and the bathroom, which a tenant in a small flat notices first. Then the windows and balcony doors on high floors, and the filters, tracks and drains that dust from nearby sites reaches. Time Properties repairs what you list in writing before you sign.
How much do I pay at the Time 2 handover?
What you pay at the Time 2 handover depends on your plan. If you are on the 10/90 plan Property Finder quotes, most of the money is paid while the tower is built; other plans leave part for after the keys. Time Properties’ fees, the service charge in advance and the DEWA deposit are added at handover.
Can I take over my Time 2 flat from abroad?
Yes. We check Time Properties’ bill and the payments still due, do the flat inspection, open the DEWA account in your name and collect the keys. If the developer requires a power of attorney, we arrange it with you remotely.
Our service
From Time Properties’ notice to a tenant in your Time 2 flat
At Time 2 we ask for your flat inspection date at once, check Time Properties’ bill against your plan, and test the cooling, the kitchen and the windows. After the keys we do the interior design, find a tenant on a yearly contract and handle the property management.
What we do for your flat
- 01
The handover with Time Properties.
- 02
The inspection for faults.
- 03
Design and furnishing.
- 04
A tenant, and the rent sent to you.
- 05
Looking after it year to year.
Free updates and a handover plan
Your handover plan for Time 2
Leave your details. We write after each new inspection of Time 2 and tell you what it means for your notice and your bill.