In Dubai Silicon Oasis · by Deyaar

Almost finished · past its date

Tria by Deyaar handover date: 94% built, next steps

Both the planned date for Tria and Deyaar’s own estimate have passed, and Deyaar has now announced the handover. Your notice is the next step, and we take it from there: the bill, the flat inspection and the keys.

BuiltChecked by the Land Department · 25 Aug 2026
94%builtPast its planned date
30 Jun 2025Planned finish date25 Aug 2026Last inspection
Tria by Deyaar, a tower with three wings at the entrance of Dubai Silicon Oasis, the developer’s renderDeveloper’s render · Deyaar

Handover date

Not set

Deyaar’s September 2026 has passed. Your handover notice gives the date that counts.

Next step

The completion certificate

Then Deyaar’s handover notice

Homes

711

Studios to 3 bedrooms, in one tower

Developer

Deyaar

Dubai Silicon Oasis

Where Tria is now, and the steps to your keys

Where Tria stands, and the steps to your keys

Tria is further along than any other building going up in Dubai Silicon Oasis, and Deyaar says the handover has begun. We send you each new inspection, and tell you when the record shows the tower finished.

7 Mar 2023
✓

Work started

The date registered with the Land Department.

30 Jun 2025
✓

Planned date

The completion date registered with the Land Department, now passed.

25 Aug 2026
✓

Last inspection

94% built.

Today

Handover announced by Deyaar in October 2026. Both the planned date and Deyaar’s own estimate have passed.

To your keys
Next

New inspection results

We send you each one the day it appears.

100% and the completion certificate

After that, Deyaar starts sending handover notices.

Handover notice

Deyaar asks for the last payment and the fees, and tells you when the flat inspection and the key collection can be booked. We book both for you.

Snagging

We check the flat before you accept the keys, and send Deyaar the list of faults.

Keys

We open the utility accounts in your name, then collect the keys. If the developer requires a power of attorney, we arrange it with you remotely.

After the keys

Furnishing

If you want it furnished, we design and furnish the flat so it is ready for a tenant.

Your first tenant

We advertise the flat, find a tenant on a yearly contract and send the rent to you abroad.

Source: Dubai Land Department.

Handover costs

What you pay Deyaar at handover, and after

At Tria the payments go on after the keys. If you are on the plan most listings quote, a small part is due at handover and almost a third over three years after it.

Last payment9% of the priceIf you are on Deyaar’s 70/30 plan: 9% at handover, then 30% over three years after it. Your sales agreement shows yours.
Deyaar’s handover and admin feesDeyaar doesn’t publish these
Service charge, paid in advanceShown on your bill
Electricity and water (DEWA)AED 2,000 deposit + about AED 130 fees
Air conditioning (cooling)The deposit depends on the company
Title deedAbout AED 250–600
Snagging (checking the flat for faults)From AED 1,599

Typical figures for 2026. Deyaar’s bill has the exact amounts, and we check them with you line by line.

Snagging

The flat inspection at Tria, before you take the keys

From Deyaar’s notice until you sign for the keys, any fault you report is Deyaar’s to repair. In this tower, four checks come before the rest.

01

Ask for your date at once

711 homes in one tower are being handed over from October 2026. The dates for the flat inspection go fast, so we ask for yours the day your notice arrives.

02

Smart controls and kitchen appliances

Listings say the flats come with smart-home controls and a fitted kitchen with appliances. We try every control and every appliance, and list anything that does not work.

03

Windows on the upper floors

Tria rises to 33 floors. High up, wind and dust find every weak seal, so we check that each window and balcony door closes tight.

04

Your own list, not Deyaar’s

Deyaar’s team began snagging the tower in 2025. A fault it missed is still yours to report, and what you list in writing before you sign is repaired before you move in.

What this means

Send Deyaar every fault in writing, with photographs, before you accept the keys. Then the repairs are Deyaar’s, at its cost, and you see each one done before you sign.

From AED 1,599 we do the flat inspection at Tria for you and send Deyaar the list, with a photograph of each fault.

Book my snagging

Furnish or not?

Furnish your Tria flat, or let it empty?

Most homes at Tria are one-beds, and hundreds of them reach the market together. Oasis Lofts, the next new building, is far behind, so tenants will weigh Tria against the older towers around it.

Tria’s homes by layout

Which is yours?

The most common home here is the 1-bed: 300 of them.

Studio18025%
1-Bed30042%
2-Bed19227%
3-Bed395%

Source: Dubai Land Department

A similar flat in another building, empty and furnished

A living room before and after furnishing, furnished
A living room before and after furnishing, empty
UnfurnishedFurnished‹ ›
  • ✓Stands out next to similar flats on rental websites
  • ✓Tenants see how they would live in it
  • ✓Ready to move into, for tenants who don’t want to buy furniture

What this means

Against older flats, a new one already looks better. When tenants can compare hundreds of one-beds in the same tower, interior design and good furniture help yours let sooner.

Tell us your layout. We send a furnishing proposal with its cost and the expected rent, so the flat is ready shortly after handover.

Furnish my property for me

Buildings around

Tria among the buildings of Dubai Silicon Oasis

The list shows what else is being built in Dubai Silicon Oasis, with each developer, and the finished buildings around Tria, older Deyaar towers among them.

Already finished

✓Coral Residence✓Ruby Residence✓Arabian Gate✓Altia One✓Pearls by Vision✓Aura Elegance

Being built

TriaYoursDeyaarWas due Jun 2025
94%
Oasis Lofts162 homesOasis Lofts PropertiesWas due Sep 2026
50%
Aura Elite79 homesAuraWas due Apr 2026
44%
Aura Prestige76 homesAuraWas due Nov 2026
40%
Oasiz 2 by Danube481 homesDanubeDue Nov 2027
31%
Oasiz 1 by Danube408 homesDanubeDue Nov 2027
30%
Solen Residence87 homesJamal LivingDue Oct 2027
22%
Timez by Danube1,163 homesDanubeDue Jul 2028
21%

Source: Dubai Land Department

What this means

No other new building nearby is close to its keys. A tenant looking here in the coming months will compare Tria with older towers such as Coral Residence and Arabian Gate, and a new flat in good order stands out against them.

The developer

How Deyaar hands over, and its record on dates

How Deyaar hands over homes, and how many of its projects are past their date.

About Deyaar

Deyaar writes to each owner when a tower is ready, with the bill and the key booking. In October 2026 it announced that Tria is being handed over. Of the 10 projects Deyaar is building, Tria is one of 2 past their planned date.

Handover

How handover is booked

BookingWith Deyaar, once the handover notice arrives
Flat inspection and keysWhere the handover notice says
Bill, payments, documentsFrom Deyaar, with the notice

Deyaar’s 38 projects in the Land Department records

  • Finished28
  • Being built, date still ahead6
  • Being built, past their date yours2
  • Being built, no finish date given2
Homes in finished projects8,599
Projects being built now10

Source: Dubai Land Department

What this means

Tria is ahead of everything else being built around it, and Deyaar says the handover has begun. The notice may already be on its way. If you live abroad, we answer it for you.

Write to us now and we check where your flat is in Deyaar’s handover, and what your notice will ask you to pay.

Get my handover plan

Location

Where Tria is: the entrance of Dubai Silicon Oasis

Tria stands at the entrance of Dubai Silicon Oasis, close to Sheikh Mohammed Bin Zayed Road and Al Ain Road. Academic City is nearby, and Downtown and the airport are a short drive.

By car

Downtown Dubai~20 min
Dubai International (DXB)~20 min

Around you

RoadsSheikh Mohammed Bin Zayed Road and Al Ain Road
NearbyDubai International Academic City
In the towerPools, gardens and a gym on the podium and the roof
AreaThe entrance of Dubai Silicon Oasis

Questions

Tria: what owners ask

Something not here? Ask us on WhatsApp; we reply within 30 minutes.

When is the Tria by Deyaar handover date?

The planned date, the completion date registered with the Dubai Land Department, was 30 June 2025 and has passed, and so has Deyaar’s own September 2026. In October 2026 Deyaar announced that it is handing over the tower. Your own date comes in Deyaar’s handover notice.

Is Tria by Deyaar delayed?

Yes, against both dates. It was built at about 2.2% a month, and with both dates gone, no target is left to check that speed against. The last inspection, in August 2026, found it 94% built, and Deyaar has since announced the handover.

What should I check in my Tria flat before accepting it?

The smart-home controls and the kitchen appliances, the windows and balcony doors on high floors, the air conditioning in each room, and every tap and drain. Deyaar repairs what you list in writing before you sign for the keys.

How much do I pay at the Tria handover?

It depends on your plan. If you are on the plan most listings quote, 70% is paid by handover, the last 9% at handover itself, and 30% is still owed over three years after it. Deyaar’s fees, the service charge in advance and the DEWA deposit are added at handover.

Can I take over my Tria flat from abroad?

Yes. We check Deyaar’s bill and the payments still to come, do the flat inspection, open the DEWA account in your name and collect the keys. If the developer requires a power of attorney, we arrange it with you remotely.

Our service

From Deyaar’s notice to a tenant in your Tria flat

At Tria we ask for your flat inspection date at once, check Deyaar’s bill and the payments that run on after the keys, and test the smart controls and appliances. Then interior design, a tenant on a yearly contract, and property management.

Illustrative photo

What we do for your flat

  1. 01

    The handover with Deyaar.

  2. 02

    The inspection for faults.

  3. 03

    Design and furnishing.

  4. 04

    A tenant, and the rent sent to you.

  5. 05

    Looking after it year to year.

Free updates and a handover plan

Your handover plan for Tria

Leave your details. We tell you where your Tria flat stands in Deyaar’s handover, and write again after each new inspection.