In Dubai Investments Park · by Reportage

Almost finished · past its date

Verdana (Phase 2) handover date: 94% built, what happens next

Verdana Phase 2, the smaller part of the first Verdana townhouses, is nearly built. Its planned date has passed with no new date from Reportage, and the latest inspection is from June. We keep track for you and handle the keys when the notice comes.

BuiltChecked by the Land Department · 3 Jun 2026
94%builtPast its planned date
31 Dec 2025Planned finish date3 Jun 2026Last inspection
A row of Verdana 2 townhouses in Dubai Investments Park, white with wooden panels, the developer’s renderDeveloper’s render · Reportage

Handover date

Not set

Your handover notice gives the date that counts.

Next step

The completion certificate

Then Reportage’s handover notice

Homes

127

4-bedroom townhouses with a roof terrace

Developer

Reportage

Dubai Investments Park

Where Verdana Phase 2 is now, and the steps to your keys

Verdana Phase 2 construction update, and every step to your keys

Verdana Phase 2 has very little left to build before its handover, and is a short way behind Phase 1 next door and Verdana Residence. We send you each new inspection on the day it is published.

Aug 2022
✓

Sales opened

Reportage opened sales of the first Verdana townhouses, Phase 2 among them, according to Bayut and Reportage’s project page. The Land Department record has no date for the start of building.

31 Dec 2025
✓

Planned date

The completion date registered with the Land Department, now passed.

3 Jun 2026
✓

Last inspection

94% built.

Today

Very nearly built, past the planned date, and still waiting for a new date from Reportage.

To your keys
Next

New inspection results

We send you each one the day it appears.

100% and the completion certificate

After that, Reportage starts sending handover notices.

Handover notice

Reportage asks for the last payment and the fees, and tells you when the townhouse inspection and the key collection can be booked. We book both for you.

Snagging

We check the townhouse, the roof and the garden levels before you accept the keys, and send Reportage the list of faults.

Keys

We open the utility accounts in your name, then collect the keys. If the developer requires a power of attorney, we arrange it with you remotely.

After the keys

Furnishing

If you want it furnished, we design and furnish the townhouse so it is ready for a tenant.

Your garden

We design it, get Reportage’s approval and build it, so the townhouse is finished when a tenant moves in. Your garden →

Your first tenant

We advertise the townhouse once it is ready, find a tenant on a yearly contract and send the rent to you abroad.

Source: Dubai Land Department.

Handover costs

Verdana Phase 2 handover costs to budget for

Plans for Verdana differ, so your sales contract says what is due at the Verdana Phase 2 handover. Reportage’s fees, a DEWA deposit, the title deed fee and service charge in advance come on top.

Last paymentAs in your sales agreementWhatever is left on your plan is due before the keys.
Reportage’s handover and admin feesReportage doesn’t publish these
Service charge, paid in advanceShown on your bill
Electricity and water (DEWA)AED 4,000 deposit + about AED 130 fees
Title deedAbout AED 250–600
Snagging (checking the townhouse for faults)Quoted for your townhouse

Typical figures for 2026. Reportage’s bill has the exact amounts, and we check them with you line by line.

Furnish or not?

Verdana Phase 2: furnish yours, or let it empty?

Your Verdana Phase 2 townhouse can be let empty or furnished. Every home here is a 4-bed with the same rooms, and Verdana Phase 1 beside it adds many more of the same, so to a tenant scrolling through, the empty ones look alike.

Verdana Phase 2’s homes by layout

Which is yours?

Every home here is a 4-Bed: 127 of them.

4-Bed127100%

Source: Dubai Land Department

A similar townhouse in another project, empty and furnished

A townhouse living room, empty and then furnished, furnished
A townhouse living room, empty and then furnished, empty
UnfurnishedFurnished‹ ›
  • ✓Stands out next to similar homes on rental websites
  • ✓Tenants see how they would live in it
  • ✓Ready to move into, for tenants who don’t want to buy furniture

What this means

Good interior design gives a tenant a reason to stop on your listing. It also lets you offer the house to people who are moving countries and own no furniture here.

Tell us your townhouse number. We send a plan for furnishing it, the cost, and the rent we would expect it to reach.

Furnish my property for me

Garden

Verdana Phase 2: from sand to a finished garden

We expect Verdana Phase 2 gardens to be bare sand at the keys, with the landscaping left to you. We design one with you, have it approved by Reportage, then build it.

Designed around how you will use it

Lawn and plantingchosen for the heat
Shade and seatinga pergola, an outdoor room
Garden lightingfor the evenings
Automatic irrigationit waters itself

The same garden, at the keys and finished

A garden at Verdana Phase 2, finished
The same garden at Verdana Phase 2, at the keys
At the keysFinished‹ ›

Whatever you plan for the house

Ready to live in

Children can play outside from the first week, and the house feels complete when you arrive.

Stands out online

Most listings next door will probably show sand. A planted garden makes your photos different from theirs.

Easier to sell

A buyer pays for a finished house and has no garden project to think about.

What this means

Nothing is built before Reportage signs off the plan. If work starts first, Reportage can ask for it to be removed, which means paying twice.

Write to us with your Phase 2 plot and we send a first garden design, with the cost of building it.

Design my garden

Buildings around

Verdana Phase 2 and the other projects in Dubai Investments Park

Two projects nearby in Dubai Investments Park are finished. Of those still going up, only Phase 1 and Verdana Residence are ahead of Verdana Phase 2.

Already finished

✓Green Community West Extension✓Schon Business Park

Being built

Verdana Residence224 homesWas due Dec 2025
96%
Verdana Phase 1178 homesWas due Dec 2025
95%
Verdana Phase 2YoursWas due Dec 2025
94%
Verdana II209 homes
56%
Olivia Residences231 homesDue Dec 2026
38%
Verdana Residence 2239 homesWas due Apr 2026
20%

Source: Dubai Land Department

What this means

Verdana Phase 1 and Verdana Residence should be ready at about the same time as Phase 2, so tenants will have a wide choice in the first months. A house that is clean, finished and listed soon after the keys is among the first they see.

The developer

Reportage handovers at Verdana: how they work and who to call

How Reportage hands over homes, and how many of its projects are past their date.

About Reportage

Reportage registered its first Verdana launch as two projects, and Phase 2 is the smaller one. Brokers also use the name Verdana Phase 2 for Verdana II, a later project that is only about half built. Check which one your sales contract names.

Handover

How handover is booked

BookingWith Reportage, once the handover notice arrives
Home inspection and keysAt the community, set out in the notice
Bill, payments, documentsFrom Reportage, with the notice

Reportage’s 25 projects in the Land Department records

  • Finished1
  • Being built, date still ahead19
  • Being built, past their date yours4
  • Being built, no finish date given1
Homes in finished projects378
Projects being built now24

Source: Dubai Land Department

What this means

Reportage has finished just one project in Dubai so far, so its handovers cannot be judged from experience. Phase 1 is a little ahead of Phase 2, and its notice is the sign that yours is near. We deal with Reportage on behalf of owners abroad.

Leave your details and we tell you when Reportage starts sending notices for Verdana, and what yours will ask for.

Get my handover plan

Location

Verdana Phase 2 location, and what is around it

Verdana Phase 2 stands beside Phase 1, inside Verdana in Dubai Investments Park. The older Green Community, with its shops, is next door. Expo City and the Route 2020 metro are close, and Emirates Road takes you into the city.

By car

Expo City Dubai~10 min
Ibn Battuta Mall~15 min
Al Maktoum Airport (DWC)~21 min
Dubai Marina~22 min
Downtown Dubai~35 min
Dubai International (DXB)~40 min

Around you

Beside itVerdana Phase 1, the other half of the first launch
SharedPools, a gym and children’s play areas
Older neighbourGreen Community and its shops
Getting outRoute 2020 metro, Emirates Road

Questions

Verdana Phase 2: what owners ask

Something not here? Ask us on WhatsApp; we reply within 30 minutes.

When is the Verdana Phase 2 handover date?

No date has been set for Verdana Phase 2. The planned date, which is the completion date registered with the Dubai Land Department, was 31 December 2025 and has passed, and Reportage has given no new one. At the inspection of 3 June 2026 the townhouses were 94% built. Your own handover notice will carry the real date.

Is Verdana Phase 2 late?

Yes, Verdana Phase 2 is past its planned date. Measured from the start of sales, it has gone up at about 2.0% a month over 46 months, and there is no date still ahead to measure that against. Finishing work usually goes slower, so only a new inspection will show how close it is.

What do I check before accepting a Verdana Phase 2 townhouse?

At Verdana Phase 2, look for water on the roof terrace after a hose test, cooling in every room, doors and windows that close tight, and drains that run freely on each floor. We do the townhouse inspection, send Reportage the faults in writing and recheck the repairs.

Does a Verdana Phase 2 townhouse come with a garden?

Not a finished one: we expect Verdana Phase 2 plots to be handed over as bare sand. We can design a garden with you, get Reportage’s approval and build it after the keys, so it is green before a tenant or your family moves in.

How much is due at the Verdana Phase 2 handover?

At Verdana Phase 2 you pay the amount your sales contract leaves for completion, Reportage’s fees, the service charge in advance, a DEWA deposit that is returned when you close the account, and the title deed fee. We go through Reportage’s bill with you before anything is paid.

Can I do the Verdana Phase 2 handover from abroad?

Yes. You pay from home, and we check the bill, do the townhouse inspection, connect DEWA in your name and pick up the keys for you. If the developer requires a power of attorney, we arrange it with you remotely.

Our service

Everything from Reportage’s first email to a finished Verdana Phase 2 home

We make sure your notice is for Phase 2 and not Verdana II, check the bill against your sales contract, and test the townhouse from the roof terrace down. Then come the garden, interior design, a tenant and property management.

Illustrative photo

What we do for your townhouse

  1. 01

    The handover with Reportage.

  2. 02

    The inspection for faults.

  3. 03

    Design and furnishing.

  4. 04

    A tenant, and the rent sent to you.

  5. 05

    Looking after it year to year.

Free updates and a handover plan

Your handover plan for Verdana Phase 2

Leave your details. When Reportage’s notice goes out, we tell you what it means for your keys and send an early estimate of your bill.