Dubai handover updates, every month
Each month we read the Land Department’s records for every Dubai project and list what changed: which buildings finished, which are close to finishing and which are past their date.
- Finished, close to finishing, late
- The Land Department’s figures, not the adverts’
- A building table in every update
- Updates on your own building by WhatsApp
October 2026
Dubai handovers in October 2026: what finished, what is next, what is late
25 buildings were recorded as finished between 1 September and late October, and 64 more are at 90% built or above. 246 are past the date the Land Department has on record.
Read the update →Dubai Land Department records, read in late October 2026.
What each month covers
Finished
Buildings the Land Department now records as completed. Handover notices follow.
Close to finishing
Buildings at 90% built or more: the next to hand over.
Running late
Buildings past their planned date, with how far each is from finishing.
Newest first
Rather hear only about yours?
Tell us your building once. We message you on WhatsApp when something changes.
Get updates on your building
Tell us your building. We message you on WhatsApp at each milestone: inspections, completion and the handover notice.