At handover

The property handover process: from completion certificate to keys

Guide7 minutes to read

A new home is handed over in a fixed order. The building gets its completion certificate, the developer sends you a notice, you pay what is left and open DEWA, the home is inspected and snagged, and then you sign and take the keys.

Starts withThe completion certificatethe building is finishedDubai Land Department
Your windowAbout 30 daysfrom the developer’s noticeDAMAC, for example
Ends withKeys and title deedafter the last paymentThe developer

1. The building is finished

The handover cannot start until the building has its completion certificate from the authority that approved it, usually Dubai Municipality. The Dubai Land Department then records the project as completed, at 100% built. You can follow this on the Land Department’s records, or on our list of every Dubai building.

2. The developer’s notice

Within weeks of completion, the developer emails a notice of completion, sometimes called the handover letter. It lists your final balance, the fees, the documents needed and the time you have to complete. DAMAC, for example, gives 30 days from the notice to pay, inspect and finish the paperwork.

Where owners get stuck

The notice goes to the email in your purchase contract. If that address is old, the deadline can pass unnoticed. Check the developer has your current details as the building nears 100%.

3. Pay what is left

You pay the final balance and the developer’s fees by bank transfer, often with the first service charge in advance. Check each line against your purchase contract and the approved service charge rate before you pay. Our handover costs guide lists every line.

4. Open DEWA and cooling

You open DEWA in your name, and the cooling account if the building has district cooling. In Dubai this comes before the keys. See the DEWA and chiller guide.

5. Inspection and snagging

You book the inspection through the developer’s app or customer care. This is the time to snag the home: list every defect, in writing, so the developer fixes it before you accept the keys. Many developers let an inspection company attend with you or for you. Our snagging checklist shows what to check.

6. Sign and take the keys

Once the payments are cleared and DEWA is on, you sign the handover forms and receive the keys, access cards and parking. If you cannot be there, someone can sign for you with a power of attorney. Defects you listed and are still open stay on record for the developer to fix.

7. After the keys

The developer applies to turn your Oqood into a title deed. You apply for a move-in permit from the building’s management before furniture arrives, and the service charge runs from the handover date. The developer remains liable for installation defects for one year from completion.

What we do

We run every step for you: we read the notice, check the bill, open DEWA, snag the home, take the keys and get it ready to live in or rent.

HANDING OVER NOW

Buildings handing over now

Owners in these buildings are going through the handover now.

All handover dates →
BuildingStageBuiltDate

Dubai Land Department inspection records, read in October 2026.

READ NEXT

Read next

QUESTIONS

The handover process, asked and answered

What is a building completion certificate?

The certificate the authority issues when a building is finished and safe to occupy. After it, the Land Department records the project as completed and the developer can start handovers.

How long does the handover take?

Usually two to six weeks from the developer’s notice to your keys, depending on how fast payments clear and when the inspection can be booked.

Can I refuse the keys if there are defects?

You can list them and ask for fixes before you sign. Minor defects are usually fixed after the keys, under the one-year defects period.

Do I have to be in Dubai?

No. The inspection can be done for you with a signed letter, and the keys with a power of attorney.

When does the service charge start?

From the handover date. Many developers collect the first year in advance with the final payment.